Oval: Deliver deposit and initial information to CMWDText Box: About 2 weeksText Box: 53 days min.Text Box: 75 days minimum per MWD Administrative CodeText Box: 75 Days Min.Text Box: 30 Days Min.Oval: IF CEQA is readyOval: CMWD Board requests final approval by MWD and approval by LAFCOOval: CMWD Board of Directors 
 Initiates annexation
Oval: MWD approves informal termsOval: Applications to MWD and LAFCO submittedOval: MWD Board grants final approvalOval: Pay Annexation FeesOval: CMWD requests Notice of Completion from LAFCOOval: Map, legal description and other documents drafted and signedText Box: About one monthOval: Annexation
records
Oval: Final approval by CMWD BoardOval: LAFCO holds public hearing and approves annexationOval: Application to MWD for conditional approvalTypical Annexation Timeline

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Most annexations require nine months or more.